INDOT says FY2026 interstate construction averaged $46M per centerline mile, up nearly 450% since FY2015
Indiana Capital Chronicle reported Oct. 2, 2026 that the Indiana Department of Transportation spent an average of $46 million to construct a centerline mile of interstate in the 2026 state fiscal year (ended June 2026), up nearly 450% from $8.4 million in fiscal 2015; the article cites inflation, supply shortages and complex projects as drivers.

Indiana Capital Chronicle reported Oct. 2, 2026 that INDOT’s average cost to construct a centerline mile of interstate was $46 million in the 2026 state fiscal year, which ended in June 2026, compared with an $8.4 million average in fiscal 2015. The article says the FY2026 average included two complicated projects: Revive I-70 in Wayne County and Safer Drive 65 in Scott and Clark counties.
The story attributes higher costs to material-price inflation, supply-chain shortages, pandemic effects, tariffs and competing demand (including from data centers), and notes the Federal Highway Administration’s national highway construction cost index rose more than 60% from 2020 through 2025. INDOT is described as bundling projects, using competitive bidding and alternative-delivery methods with early contractor involvement; INDOT spokeswoman Natalie Garrett is cited on those practices and their aims.
Report a correction · Editorial standards · Our source directory
BusinessIndy examines this development and its implications for Indiana businesses and communities using the linked sources.
Related coverage
- FHCCI: 24,938 eviction filings in Marion County in 2025 spotlight rising corporate landlord filings in Indianapolis
- Givaudan to build $215M liquid-production plant on Indiana–Ohio border, plans 250+ jobs
- Purdue’s Indianapolis Academic Success Building tops out; project now over 60% complete, finishing by fall 2027
Reader discussion
Join the discussion. Every comment is checked before publication. Community rules and appeals